i. the establishment of the online export permit system is 90% complete, with some mines having been identified for trial runs of the system;
ii. the wire making line at Dinson Iron and Steel Company at Manhize in Midlands Province is 75% complete, while the mill balls are 60%. Some of the steel products being produced at Dinson include pig iron, rebar, hot-rolled wire rods, and hot rolled round bars;
iii. the construction of the Platinum Group Metals Concentrate Smelter Expansion Project and the 35 MW Phase 1 Solar Plant at ZIMPLATS is complete;
iv. the US$34 million Cesium Flotation Plant at Sinomine Bikita, Masvingo is under commissioning;
v. the Mutagech Coking Plant, Hwange in Matabeleland North Province is now operational with a washing plant capacity of 200 000 metric tonnes per month;
vi. the construction of a coking plant at Zambezi Gas and Coal Mine in Hwange has reached 95% of completion;
vii. the establishment of a Coke Oven Battery at Zimbabwe Zhong-Xin in Hwange is 90% complete;
viii. the underground mine developed at Hwange Colliery Company is now fully operational and the refurbishment of Coke Oven Batteries stand at 95% of completion; the consolidated Petroleum Production Sharing Agreement and Petroleum Exploration and Production Agreement for the Muzarabani Oil and Gas Project is now in place, and the project was granted National Project Status;
x. the construction of a Platinum Group Metals Concentrator at Karo Platinum in Mashonaland West is in progress having reached 41%;
and
xi. the construction of Coking, Power and Ferrochrome plants at Palm River Mine in Beitbridge is now complete.